Turnberry Park Project

The city is planning to increase access and recreational opportunities to the Turnberry neighborhood park spring of 2023. To date, the city has conducted a neighborhood connectivity study, site topographic survey, soil investigation, wetland delineation, and tree survey. Ideas being considered include:

  • Quality tree preservation
  • Wetland areas will not be considered as possible amenity areas
  • Explore connection to existing dead-end trail connections to the north and east 
  • Explore additional trail connections to the south
  • Include amenities like benches, picnic tables, and a dog sanitation station
  • Evaluate interest in additional park amenities

These elements, combined with the input received via the project public engagement opportunities, will serve as the basis for the upcoming design.

Incorporation of feedback received in August 2022, and initial review by the Parks and Natural Resources Commission (PNRC), resulted in the creation of a final concept plan. This final concept plan was presented to the PNRC for approval in December 2022.

Project Schedule

DatesItem
December 2022Seek approval for updated concept plan
Winter 2023Project bidding and contract approval
March 2023Resources management as necessary
Spring 2023Project installation
Summer 2023Construction
Late summer 2023Anticipated project completion
2023-2028Natural resource/vegetation management