Dale Road Project

Planning is currently underway for future roadway improvements to Dale Road from Radio Drive to Copper Ridge Drive to support development in the area. The project goals are to improve safety and traffic flow for all users, including pedestrians, bicyclists, and vehicles. A two-lane divided roadway with paved trails is proposed to meet the project goals.

Project Open Houses

In-Person

Join project coordinators Thursday, Sept. 28, from 4:30-6:30 p.m. at Eagle Valley Golf Course Clubhouse to learn more and ask questions about the project. 

Virtual 

A virtual open house will be held Thursday, Oct. 5, from 11 a.m.-noon. A Zoom link for the virtual open house will be provided on this website prior to the meeting. 

Tentative Project Timeline

ItemAnticipated Date
Planning and preliminary designFall 2022-Fall 2023
Detailed design and development for final engineering documentsFall 2023-Spring 2024
Easement Acquisitions Spring 2024
Construction Begins2025